International Representation Archives - GCE Group /project-type/international-representation/ An Investment, Trading and Agency House Sun, 26 Feb 2023 06:18:22 +0000 en-US hourly 1 Kathmandu-Terai/Madhesh Fast Track (Expressway) Road Project /project/kathmandu-terai-madhesh-fast-track-expressway-road-project/ Fri, 18 Feb 2022 08:53:50 +0000 /?post_type=project&p=278   The Kathmandu Terai/Madhesh Fast Track (KTFT) (Expressway), that links Kathmandu valley to Terai intends to improve the transport reliability by providing a cost effective investment to improve links between Kathmandu with border points with northern and southern neighbors so that there is a considerable savings in both travel time and cost. This link is... Read more »

The post Kathmandu-Terai/Madhesh Fast Track (Expressway) Road Project appeared first on GCE Group.

]]>
 

The Kathmandu Terai/Madhesh Fast Track (KTFT) (Expressway), that links Kathmandu valley to Terai intends to improve the transport reliability by providing a cost effective investment to improve links between Kathmandu with border points with northern and southern neighbors so that there is a considerable savings in both travel time and cost. This link is envisaged to be of Asian Highway Standard (Primary Class).

With the support of GCE Group, China State Construction Engineering Corporation has won the contract for Planning, Design, Engineering, Procurement, Construction and Commissioning of Twin Double Lane Standard Expressway Tunnel, Bridges and Expressway Works on Engineering, Procurement and Construction (EPC) Contract basis all complete.

The post Kathmandu-Terai/Madhesh Fast Track (Expressway) Road Project appeared first on GCE Group.

]]>
Mistri Khola Hydroelectric Project /project/mistri-khola-hydroelectric-project/ Thu, 22 Apr 2021 10:18:51 +0000 /?post_type=project&p=247 Mistri Khola Hydroelectric Project (MKHEP or Project) is a run-of- the-river type project on the Mistri Khola, a major tributary of the Kaligandaki River. It is located in Myagdi district of Nepal. The project is completed and is in Operation. With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning... Read more »

The post Mistri Khola Hydroelectric Project appeared first on GCE Group.

]]>
Mistri Khola Hydroelectric Project (MKHEP or Project) is a run-of- the-river type project on the Mistri Khola, a major tributary of the Kaligandaki River. It is located in Myagdi district of Nepal. The project is completed and is in Operation.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Mistri Khola Hydroelectric Project had been awarded to VOITH Hydro Pvt. Ltd.

The post Mistri Khola Hydroelectric Project appeared first on GCE Group.

]]>
Nupche Likhu Hydropower Project /project/nupche-likhu/ Tue, 20 Apr 2021 07:09:20 +0000 /?post_type=project&p=229 The source of water for Nupche Likhu hydropower project is originated from snow fed rivers starting from the High Mountain/Hilly areas. The proposed Nupche Likhu Hydropower Project is located in Gumdel VDC (Currenty Umakunda Rural Municipality) of Ramechhap District, Nepal. The proposed intake of the Nupche Likhu Hydropower Project is located north of Lahaksewar village... Read more »

The post Nupche Likhu Hydropower Project appeared first on GCE Group.

]]>
The source of water for Nupche Likhu hydropower project is originated from snow fed rivers starting from the High Mountain/Hilly areas.

The proposed Nupche Likhu Hydropower Project is located in Gumdel VDC (Currenty Umakunda Rural Municipality) of Ramechhap District, Nepal. The proposed intake of the Nupche Likhu Hydropower Project is located north of Lahaksewar village in left bank of Nupche Khola at an elevation of 3330 m above msl.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Nupche Likhu Hydro Power Project had been awarded to VOITH Hydro Pvt. Ltd.

The post Nupche Likhu Hydropower Project appeared first on GCE Group.

]]>
Solu Khola (Dudhkoshi) Hydroelectric Project /project/solu-khola-hydroelectric-project/ Mon, 19 Apr 2021 11:32:01 +0000 /?post_type=project&p=226 Solu Khola (Dudhkoshi) Hydroelectric Project (SKDKHEP) is an 86 MW Run Of River (RoR) type of project located at Solududhkunda Municipality & Thulung Dudh Koshi Gaupalika (Former Tingla, Kangel & Panchan VDCs) of Solukhumbu District, Sagarmatha Zone, Nepal. The project area is about 130 km (aerial) east of Kathmandu. With the assistance of GCE Group,... Read more »

The post Solu Khola (Dudhkoshi) Hydroelectric Project appeared first on GCE Group.

]]>
Solu Khola (Dudhkoshi) Hydroelectric Project (SKDKHEP) is an 86 MW Run Of River (RoR) type of project located at Solududhkunda Municipality & Thulung Dudh Koshi Gaupalika (Former Tingla, Kangel & Panchan VDCs) of Solukhumbu District, Sagarmatha Zone, Nepal. The project area is about 130 km (aerial) east of Kathmandu.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Rasuwagadhi Hydro Power Project had been awarded to VOITH Hydro Pvt. Ltd.

The post Solu Khola (Dudhkoshi) Hydroelectric Project appeared first on GCE Group.

]]>
Chatara Hydropower Project /project/chatara-hydropower-project/ Fri, 13 Sep 2019 04:37:14 +0000 /?post_type=project&p=194 Chatara Hydropower Station, a canal drop type power station, is located at Chatara, Sunsari with installed capacity of 3.2 MW and annual design generation of 6 GWh. It was commissioned in 1996 AD in assistance from Government of India at a cost of NRs. 162.6 million and was handed over to NEA by Sunsari Morang... Read more »

The post Chatara Hydropower Project appeared first on GCE Group.

]]>
Chatara Hydropower Station, a canal drop type power station, is located at Chatara, Sunsari with installed capacity of 3.2 MW and annual design generation of 6 GWh. It was commissioned in 1996 AD in assistance from Government of India at a cost of NRs. 162.6 million and was handed over to NEA by Sunsari Morang Irrigation Project (SMIP) on 29 March, 1999. However, the power station has not undergone any major overhauling since the plant was brought into operation in 1996. The inconveniences to access the turbine assembly and the inability of gates and stop logs to seal the water have restricted the regular maintenance of the units. Team of in-house experts after visiting the site has given recommendations in connection with the repair and maintenance of the turbines. Based on recommendations, the power station has planned to carry out the overhauling of Unit No. 2 this year after procuring the additional spare parts and in coordination with Sunsari-Morang Irrigation Project, Biratnagar.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Chatara Hydropower Project was awarded to Sulzer Ltd, Germany.

The post Chatara Hydropower Project appeared first on GCE Group.

]]>
Chilime Hydropower Plant /project/chilime-hydropower-plant/ Thu, 05 Sep 2019 07:09:20 +0000 /?post_type=project&p=189 The Chilime Hydropower Plant is a peaking run off river type plant constructed and owned by Chilime Hydropower Company Limited. It is located at 133 km north of Kathmandu at the right bank of Bhotekoshi River in Rasuwa District. The plant with the installed capacity of 22.1 MW is delivering power to the National Grid... Read more »

The post Chilime Hydropower Plant appeared first on GCE Group.

]]>
The Chilime Hydropower Plant is a peaking run off river type plant constructed and owned by Chilime Hydropower Company Limited. It is located at 133 km north of Kathmandu at the right bank of Bhotekoshi River in Rasuwa District. The plant with the installed capacity of 22.1 MW is delivering power to the National Grid through a 38 km long 66 kV single circuit transmission line at Trisuli Power House Switchyard at Trishuli, Nuwakot.

The electricity generated from the power plant is purchased by NEA at the powerhouse and evacuated as per the PPA made on June 25, 1997 and its first amendment made dated December 10, 2007. The annual deemed energy salable to NEA is 132.918 GWh, excluding penalty-free outage of 720 MWh (36hours) annually.

The plant has started its commercial generation from 00:00 hours of 24th August 2003. During 17 years of its operation, the plant has been operating successfully.

With the support of GCE Group,  VA Tech has won the contract for the turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for this project.

The post Chilime Hydropower Plant appeared first on GCE Group.

]]>
Narayanghat-Butwal Road Improvement Project /project/sasec-roads-improvement-project-narayanghat-butwal-highway-road-improvement-project/ Wed, 04 Sep 2019 11:17:26 +0000 /?post_type=project&p=186 SASEC Roads Improvement Project: The Narayanghat-Butwal road is the part of East West Highway. It passes through Chitwan, Nawalparasi and Rupandehi districts. The road starts at Pulchowk of Narayanghat (Chitwan district) and ends at Chauraha of Butwal (Rupandehi district). The total length of the road is 115 km. The project includes major activities, which includes... Read more »

The post Narayanghat-Butwal Road Improvement Project appeared first on GCE Group.

]]>
SASEC Roads Improvement Project: The Narayanghat-Butwal road is the part of East West Highway. It passes through Chitwan, Nawalparasi and Rupandehi districts. The road starts at Pulchowk of Narayanghat (Chitwan district) and ends at Chauraha of Butwal (Rupandehi district). The total length of the road is 115 km. The project includes major activities, which includes drainage improvement, minor realignment, pavement improvement and widening of the existing road in to 4 lanes with intermediately service lane in both sides.

With the support of GCE Group, China State Construction Engineering Corporation has won the contract paper writings to upgrade the highway. The work is being financed by the Asian Development Bank.

The post Narayanghat-Butwal Road Improvement Project appeared first on GCE Group.

]]>
Likhu-4 Hydropower Project /project/likhu-4-hydropower-project/ Mon, 02 Sep 2019 06:16:36 +0000 //?post_type=project&p=176 Likhu IV is  52.4 MW run-of-river hydro electric project along Likhu River and is located around 220 KM from Kathmandu, capital of Nepal. The project has favorable hydrology and is easily accessible. The project is being developed by Green Ventures Pvt. Ltd which is a joint venture between Bhilwara Energy Limited and Triveni Group of... Read more »

The post Likhu-4 Hydropower Project appeared first on GCE Group.

]]>
Likhu IV is  52.4 MW run-of-river hydro electric project along Likhu River and is located around 220 KM from Kathmandu, capital of Nepal. The project has favorable hydrology and is easily accessible. The project is being developed by Green Ventures Pvt. Ltd which is a joint venture between Bhilwara Energy Limited and Triveni Group of Nepal.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Likhu-4 Hydro Power Project had been awarded to VOITH Hydro Pvt. Ltd.

The post Likhu-4 Hydropower Project appeared first on GCE Group.

]]>
Rasuwagadhi Hydroelectric Project /project/rasuwagadhi-hydroelectric-project/ Mon, 02 Sep 2019 06:12:41 +0000 //?post_type=project&p=175 Rasuwagadhi Hydroelectric Project (RGHEP) is a 111 MW Run of River hydroelectric scheme located in Rasuwa District, approximately 150 km north of Kathmandu. The project consists of a diversion weir, underground desander chambers, a 4 km long headrace tunnel, an underground powerhouse complex, 3 vertical axis francis turbines and 132kV double circuit transmission line. With... Read more »

The post Rasuwagadhi Hydroelectric Project appeared first on GCE Group.

]]>
Rasuwagadhi Hydroelectric Project (RGHEP) is a 111 MW Run of River hydroelectric scheme located in Rasuwa District, approximately 150 km north of Kathmandu.

The project consists of a diversion weir, underground desander chambers, a 4 km long headrace tunnel, an underground powerhouse complex, 3 vertical axis francis turbines and 132kV double circuit transmission line.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Rasuwagadhi Hydro Power Project had been awarded to VOITH Hydro Pvt. Ltd.

The post Rasuwagadhi Hydroelectric Project appeared first on GCE Group.

]]>
Lower Hewa Hydropower Project /project/lower-hewa-hydropower-project/ Mon, 02 Sep 2019 05:55:05 +0000 //?post_type=project&p=173 Lower Hewa Khola Hydropower Project (LHKHPP) (developed by Mountain Hydro Nepal Pvt. Ltd) is located in Panchthar District of Eastern Development Region of Nepal.  The project is a run-of-river type in which water will be diverted from the Hewa Khola and the Pheme Khola just upstream of their confluence, by constructing concrete weir at hewa... Read more »

The post Lower Hewa Hydropower Project appeared first on GCE Group.

]]>
Lower Hewa Khola Hydropower Project (LHKHPP) (developed by Mountain Hydro Nepal Pvt. Ltd) is located in Panchthar District of Eastern Development Region of Nepal.  The project is a run-of-river type in which water will be diverted from the Hewa Khola and the Pheme Khola just upstream of their confluence, by constructing concrete weir at hewa and boulder rip-rap at Pheme. The Combined design discharge of project is 14.838 m3/s with 40% probability of exceedance level will be diverted for power generation through the side intakes located at left banks of Hewa Khola and Pheme Khola respectively. This project utilizes a gross head of 178.09 m in between the intakes at an elevation of 636.09masl and tailwater level 458.00 masl. The total length of the waterways including intakes, approach canals, settling basins, headrace tunnel, penstock pipe and tailrace will be about 6039 m.

With the assistance of GCE Group, Turnkey contract for Supply Delivery, Erection, Installation & Commissioning of Electro-mechanical equipment for Lower Hewa Hydropower Project had been awarded to VOITH Hydro Pvt. Ltd.